In a non-infill system, cushioning comes from the turf fibers, backing, any integrated or separate shock pad, and the supporting base. A product with an integrated foam backing may not require an additional pad, while a field installed over a hard base may benefit from a separately specified cushioning layer.
The key is not simply whether a pad is included. The complete system should provide suitable impact attenuation and vertical deformation without compromising stability or drainage.
1. Three Common Scenarios
Scenario 1: A school football or multi-purpose field over concrete or asphalt
Concrete and asphalt provide little impact attenuation. For fields used for running, ball games and frequent physical education activities, a separate shock pad is often worth considering.
The required configuration should be determined by the intended activities, the complete system’s test results and the applicable project requirements—not by the base material alone.
Scenario 2: Turf with an integrated foam backing
Some non-infill products incorporate a cushioning layer into the backing, creating an integrated turf-and-cushioning system.
This may eliminate the need for a separate shock pad, but the presence of foam is not proof of adequate performance. Schools should review test data for the complete system and confirm that it is suitable for the intended use.
Scenario 3: Landscaping, buffer zones or low-intensity areas
A separate shock pad may not be necessary in areas used mainly for landscaping, resting or low-intensity activities. However, if students also run, play or take part in regular physical education in these areas, the cushioning requirements should be reassessed.
2. Why Is Cushioning Important in a Non-Infill System?
In an infill system, the infill contributes to the surface’s performance. In a non-infill system, the load path is generally:
Footwear → turf fibers → backing → any cushioning layer → foundation
The fibers and backing provide some cushioning, but their capacity is limited. A suitable shock pad can add controlled deformation and help dissipate impact energy.
A shock pad may also:
Help balance impact attenuation and surface stability.
Reduce localized stress on the turf backing and seams.
Contribute to drainage when its design forms part of the system’s drainage path.
Accommodate some minor irregularities, although it cannot replace proper foundation preparation.
A pad should not be selected simply because it is thick or soft. If it is too compliant, the surface may feel unstable, equipment supports may sink, and ball response may change. If it is too thin or too stiff, the system may not provide the intended cushioning.
The correct choice depends on how the pad works with the turf and foundation as a complete system.
3. Four Shock-Pad Details to Review
Item | What to check | Why it matters |
|---|---|---|
Thickness | Specified thickness for the proposed system | Thickness alone does not establish performance |
Density and compression behavior | Relevant material data and system test results | Helps assess support, deformation and recovery |
Perforations and drainage design | Openings, channels or other drainage features | Affects water movement and the risk of trapped water |
Joints and installation | Joint layout, bonding or fixing method | Helps prevent movement, ridges and uneven areas |
Some projects use separate pads around 10–15 mm thick, and some closed-cell PE products are specified at densities around 40–50 kg/m³. These are examples, not universal recommendations. The appropriate values depend on the product, field use, foundation and performance requirements.
4. Turning “Shock Pad Included” into “System Properly Specified”
Specify system performance, not just a material list
A tender that only states turf height and shock-pad thickness can encourage price comparisons based on isolated components.
Instead, specify the required performance of the complete field, including relevant impact attenuation, vertical deformation, tuft bind and water permeability requirements. Identify the applicable test methods and acceptance process.
Test the finished system and inspect the installed field
Material tests can help verify supplied products, but they do not necessarily demonstrate how the completed system performs.
Where required, arrange finished-field testing for the installed configuration. Test locations should represent different use areas, such as regular activity zones, goal areas and perimeter sections, rather than relying on one convenient location.
Inspect concealed work before it is covered
Before the turf is installed, review:
Foundation preparation, compaction and evenness.
Shock-pad joints and fixing.
Contact between the pad and the turf system.
Drainage gradients, outlets and flow paths.
These details become difficult to inspect after the surface is completed. Problems with joints, levels or drainage can lead to movement, unevenness or water accumulation later.
Coordinate drainage and finished levels from the start
The shock pad may form part of the drainage path, depending on its design. The foundation levels, gradients, permeability and outlets should therefore be coordinated during design.
A shock pad cannot correct a poorly designed drainage system, and adding one without reviewing finished levels can create avoidable problems.
5. Common Misunderstandings
“A thicker pad is always safer.”
Not necessarily. Excessive softness or deformation can affect stability and ball response. The complete system should be tested against the requirements for its intended use.
“Recycled foam or low-cost reclaimed material is good enough.”
Material consistency, durability, compression set and chemical performance can vary. Schools should assess documentation and test results rather than choosing by price alone.
“The pad does not need to be secured.”
Movement, raised joints or ridges can affect the surface and contribute to seam or edge problems. The specified installation method should be followed.
“More holes always mean better drainage.”
Perforation must be balanced with support and structural performance. Drainage depends on the entire system, including the foundation and outlets.
“A shock pad means the foundation no longer matters.”
An uneven or inadequately compacted base can still create unevenness and localized movement. The pad does not replace proper foundation construction.
6. A Five-Point Checklist for Schools
Request test data for the complete turf system, not just separate material reports.
Confirm the pad’s thickness, density, compression behavior and drainage design, and check compatibility with the turf.
Verify the joint and fixing method, including how the pad is secured at seams and edges.
Review comparable school installations, focusing on years in service and maintenance history, not just field size.
Include finished-field inspection or testing, warranty scope and maintenance responsibilities in the contract.
7. Considering VivaTurf Non-Infill Artificial Turf
For schools seeking a complete solution that coordinates turf, cushioning and foundation drainage, VivaTurf is a manufacturer worth including in the supplier comparison.
The supplied product description identifies a straight-and-curly fiber structure paired with a closed-cell PE composite shock pad. It also describes selecting the pad’s density and compression properties to suit the turf system, rather than simply increasing thickness. These details should be confirmed for the exact product and project being offered.
Schools can ask VivaTurf for the proposed system configuration, relevant test reports and installation guidance. The documentation should show whether the complete system meets the project’s performance requirements, including impact attenuation, vertical deformation and drainage.
The supplied draft also refers to school football and multi-purpose fields as application examples. Before using specific projects in public-facing material, verify the project details and obtain permission to identify the schools. Past use alone does not establish suitability for every site.
Whether a school’s non-infill artificial turf field needs a shock pad depends on how the system provides cushioning and whether its performance can be demonstrated through appropriate testing.
A separate pad is often worth considering for active school fields, especially over hard foundations. But an integrated cushioning system may also be suitable if its complete-system performance is verified.
The decision should be based on the intended activities, the complete system’s test results and the foundation and drainage design—not simply on whether a pad is included.